Download NCARB Project-Management Exam Dumps Demo Free of Cost
BONUS!!! Download part of DumpsQuestion Project-Management dumps for free: https://drive.google.com/open?id=1b50Hily51X428jiqm8RendzxNEmGwAcL
If you want to pass the Project-Management exam, our Project-Management practice questions are elemental exam material you cannot miss. It is proved by our loyal customers that our passing rate of Project-Management practice materials has reached up to 98 to 100 percent up to now. Besides, free updates of Project-Management Exam Torrent will be sent to your mailbox freely for one year, hope you can have a great experience during usage of our Project-Management practice materials.
We know that consumers want to have a preliminary understanding of the product before buying it. So, before you buy our Project-Management exam braindumsp, we will offer you three different versions of the trial. They are free demos. At the same time, the installation and use of our Project-Management Study Materials is very safe and you don't need to worry about viruses. We will also protect your personal privacy sufficiently. And we will give you the best service on our Project-Management practice engine.
>> Certification Project-Management Training <<
ARE 5.0 Project Management (PjM) Exam updated pdf material & Project-Management exam training vce & online test engine
With the protection of content and learning methods on our Project-Management study guide, you will not have to worry about your exam at all. Of course, if you have any suggestions for our Project-Management training materials, you can give us feedback. Our team of experts will certainly consider your suggestions. Perhaps the next version upgrade of Project-Management Real Exam is due to your opinion. In order to thank you for your support, we will also provide you with some benefits.
NCARB ARE 5.0 Project Management (PjM) Exam Sample Questions (Q61-Q66):
NEW QUESTION # 61
An architect is working on a design-build project for a large skyscraper. The architect has completed a conceptual design, finalized the contracts, and hired consultants. The schematic design phase is set to begin in one week.
Which items or tasks are important for the architect to complete during this time? Check the three that apply.
Answer: A,C,D
Explanation:
Verified Answer
At the outset of schematic design, the architect must coordinate with consultants and communicate constraints and expectations to keep the project aligned with goals. Building permits are typically addressed in the construction documents phase. FF&E coordination and curtain wall detailing occur later in design development and construction documents.
Coordination and planning at schematic design are crucial to project integration.
Reference: AIA B101 §3.2 - Schematic Design Phase
NCARB ARE 5.0 Handbook - PjM Content Area 1 and 4
NEW QUESTION # 62
What is the architect's responsibility regarding code compliance during design?
Answer: C
Explanation:
The architect is responsible for preparing design documents that comply with applicable codes and regulations. Structural design is typically performed by engineers. Permitting and inspections are government responsibilities. Ensuring documents meet code requirements reduces the risk of delays or rework. ARE 5.0 PjM tests understanding of code compliance roles.
NEW QUESTION # 63
A project achieves refinement and coordination in which of the following phases?
Answer: B
Explanation:
Design Development (DD) is the phase where schematic concepts are refined and systems are coordinated across disciplines. This includes structure, MEP, and materials. While Schematic Design focuses on high- level form and layout, and Construction Documents focus on detailed drawings/specifications, DD ensures integration and alignment before detailing.
References:
NCARB ARE 5.0 Handbook - Design phases
AIA B101 - Design Development phase scope
NEW QUESTION # 64
The architect's estimate of the cost of the work at the end of the construction documents phase exceeds the owner's stated budget for the cost of the work.
According to AIA Document B101, what should the architect recommend to the owner?
Answer: B
Explanation:
Verified Answer
According to AIA Document B101 §6.7, if the lowest bona fide bid or negotiated proposal exceeds the budget, the architect is required to make reasonable modifications to bring the cost in line with the budget - at no additional compensation - provided the architect's cost estimate was based on current market conditions.
* This clause ensures the architect takes responsibility for staying within budget expectations.
* Reference: AIA B101-2017 §6.7
* NCARB ARE 5.0 Handbook - PjM Content Area 2: Cost Estimating and Budgeting
NEW QUESTION # 65
During the preparation of the construction documents, it was noted that the survey inaccurately located the property line. Consequently, the parking layout had to be redesigned to fit within the corrected property boundary.
The architect's additional costs and associated delay are the responsibility of which one of the following parties?
Answer: D
Explanation:
According to AIA B101 §5.1, the owner is responsible for providing the site survey and other site-related documentation. If the survey is inaccurate and causes delays or extra services, the owner is responsible for costs incurred. The architect should submit a claim for additional services.
* Surveyors are contracted by the owner (not by the architect unless explicitly stated).
* The architect is not liable for incorrect information furnished by the owner.
* Reference: AIA B101 §5.1 and §3.6
* NCARB ARE 5.0 Handbook - PjM Content Area 2: Budget and Contracts
====================
NEW QUESTION # 66
......
We assure that you can not only purchase high-quality Project-Management prep guide but also gain great courage & trust from us. A lot of online education platform resources need to be provided by the user registration to use after purchase, but it is simple on our website. We provide free demo of Project-Management guide torrent, you can download any time without registering. We can’t say we are the absolutely 100% good, but we are doing our best to service every customer. Only in this way can we keep our customers and be long-term cooperative partners. Looking forwarding to your Project-Management Test Guide use try!
Valid Project-Management Exam Question: https://www.dumpsquestion.com/Project-Management-exam-dumps-collection.html
NCARB Certification Project-Management Training So, you are more willing to study, and once you have taken all essential knowledge in training material, you are supposed to make your exam successfully, NCARB Certification Project-Management Training We assist about 56297 candidates to pass exams every year, Our Project-Management practice dumps are so popular that all our customers are giving high praise on its high-quality to help them pass the exams, Our Project-Management exam material is good to pass the exam within a week.
Once the worm finds a computer to infect, it then drops Project-Management the code onto the system to join it to the botnet, Presenting Data with Summary and Subsummary Reports, So, you are more willing to study, and once you have Valid Project-Management Exam Question taken all essential knowledge in training material, you are supposed to make your exam successfully.
100% Pass Quiz NCARB - Newest Project-Management - Certification ARE 5.0 Project Management (PjM) Exam Training
We assist about 56297 candidates to pass exams every year, Our Project-Management practice dumps are so popular that all our customers are giving high praise on its high-quality to help them pass the exams.
Our Project-Management exam material is good to pass the exam within a week, With the NCARB Project-Management exam dumps, you can not only validate your skill set but also get solid proof of your proven expertise and knowledge.
DOWNLOAD the newest DumpsQuestion Project-Management PDF dumps from Cloud Storage for free: https://drive.google.com/open?id=1b50Hily51X428jiqm8RendzxNEmGwAcL